Certified Credit Research Analyst - Level 2 exams.
Question - (Single Choise)
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro
power project on river Shivna in Madhya Pradesh (MP). The project is also of relevance from the
irrigation perspective due to its location and as per the agreement MCC will have to undertake
construction of web of canals, approach road to dam, power house and other ancillary units. MCC is
promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed
government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges
and railway platforms on contract basis for the Government. MCC will have a separate special
purpose vehicle (SPV) floated for this venture.
The hydro power project comes under the public private partnership scheme of the Government of
MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant.
The detailed terms of the hydro power project agreement are as follows:
1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor.
The
Government of MP will have to acquire land which will submerge on construction of dam and shall
rehabilitate the owners of land.
2. MCC shall have right to operate the hydro power project from date of commencement of
commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government
thereafter. Further,
SPV shall be tax exempt for a period of five years from DCCO i.e. FY17 - FY21.
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The
estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project
is estimated to be commercially operational by April 1, 2016 with two units operational on same day
and one unit each will be operational on April 1, 2017 and April 1, 2018.
4. Means of finance:
Means of Finance INR Million
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100
5. Amount if expenditure estimated in various years is as follows:
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the
principal. The expected principal along with capitalized interest is expected to be INR2, 400 Million
(i.e.INR2100 Million debt plus INR300 Million capitalized interest). The repayment of the same shall
be in 12 equated annual installments starting from FY17.
Brief projections for the period of FY17 to FY21 are given below:
Developments as on March 31, 2015
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From
today we are just left with one more year to complete the project in time. However, the flash floods
which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point
out the loss of lives in the region as you all are well aware of those. Our project has also been badly
hit due to the same and we have been assessing the damage over the last one week. After analyzing
damage, we have made changes in project schedule. Now we will be making only one unit of 150
MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s).
Development as on September 30, 2015
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to
construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in
various courts.
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region
and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its
press release has indicated that they will apply to the higher court on the matter.
As a credit analyst on March 31, 2012, which of the following sets of risks are you going to put in your
credit appraisal note?
Question - (Single Choise)
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro
power project on river Shiva in Madhya Pradesh (MP). The project is also of relevance from the
irrigation perspective due to its location and as per the agreement MCC will have to undertake
construction of web of canals, approach road to dam, power house and other ancillary units. MCC is
promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed
government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges
and railway platforms on contract basis for the Government. MCC will have a separate special
purpose vehicle (SPV) floated for this venture.
The hydro power project comes under the public private partnership scheme of the Government of
MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant.
The detailed terms of the hydro power project agreement are as follows:1. The construction of the
dam, canals and hydro power plant shall be undertaken by the contractor. The
Government of MP will have to acquire land which will submerge on construction of dam and shall
rehabilitate the owners of land.
2. MCC shall have right to operate the hydro power project from date of commencement of
commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government
thereafter. Further,
SPV shall be tax exempt for a period of five years from DCCO i.e. FY17 - FY21.
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The
estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project
is estimated to be commercially operational by April 1, 2016 with two units operational om same day
and one unit each will be operational on April 1, 2017 and April 1, 2018.
4. Means of finance:
Means of Finance INR Million
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100
5. Amount if expenditure estimated in various years is as follows:
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the
principal. The expected principal along with capitalized interest is expected to be INR2, 400 Million
(i.e.INR2100 Million debt plus INR300 Million capitalized interest). The repayment of the same shall
be in 12 equated annual installments starting from FY17.
Brief projections for the period of FY17 to FY21 are given below:
Developments as on March 31, 2015
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From
today we are just left with one more year to complete the project in time. However, the flash floods
which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point
out the loss of lives in the region as you all are well aware of those. Our project has also been badly
hit due to the same and we have been assessing the damage over the last one week. After analyzing
damage, we have made changes in project schedule. Now we will be making only one unit of 150
MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s).
Development as on September 30, 2015
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to
construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in
various courts.
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region
and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its
press release has indicated that they will apply to the higher court on the matter.
Based on the initial projections, do scenario analysis assuming only 75% capacity is utilized in FY17
and FY18 and thereby revenues will be proportionally reduced.
Compute DSCR under such scenario for FY17 and FY18, assuming other things remain constant?
Question - (Single Choise)
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro
power project on river Shivna in Madhya Pradesh (MP). The project is also of relevance from the
irrigation perspective due to its location and as per the agreement MCC will have to undertake
construction of web of canals, approach road to dam, power house and other ancillary units. MCC is
promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed
government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges
and railway platforms on contract basis for the Government. MCC will have a separate special
purpose vehicle (SPV) floated for this venture.
The hydro power project comes under the public private partnership scheme of the Government of
MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant.
The detailed terms of the hydro power project agreement are as follows:
1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor.
The
Government of MP will have to acquire land which will submerge on construction of dam and shall
rehabilitate the owners of land.
2. MCC shall have right to operate the hydro power project from date of commencement of
commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government
thereafter. Further,
SPV shall be tax exempt for a period of five years from DCCO i.e. FY17 - FY21.
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The
estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project
is estimated to be commercially operational by April 1, 2016 with two units operational om same day
and one unit each will be operational on April 1, 2017 and April 1, 2018.
4. Means of finance:
Means of Finance INR Million
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100
5. Amount if expenditure estimated in various years is as follows:
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the
principal. The expected principal along with capitalized interest is expected to be INR2, 400 Million
(i.e.INR2100 Million debt plus INR300 Million capitalized interest). The repayment of the same shall
be in 12 equated annual installments starting from FY17.
Brief projections for the period of FY17 to FY21 are given below:
Developments as on March 31, 2015
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From
today we are just left with one more year to complete the project in time. However, the flash floods
which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point
out the loss of lives in the region as you all are well aware of those. Our project has also been badly
hit due to the same and we have been assessing the damage over the last one week. After analyzing
damage, we have made changes in project schedule. Now we will be making only one unit of 150
MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s).
Development as on September 30, 2015
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to
construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in
various courts.
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region
and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its
press release has indicated that they will apply to the higher court on the matter.
After the developments of March 31, 2015, assuming revenues are directly linked to the power
production and the EBITDA margins remain intact for the year, as were projected, compute the
revised interest coverage ratio dfor FY17 and FY18?
Question - (Single Choise)
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro
power project on river Shivna in Madhya Pradesh (MP). The project is also of relevance from the
irrigation perspective due to its location and as per the agreement MCC will have to undertake
construction of web of canals, approach road to dam, power house and other ancillary units. MCC is
promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed
government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges
and railway platforms on contract basis for the Government. MCC will have a separate special
purpose vehicle (SPV) floated for this venture.
The hydro power project comes under the public private partnership scheme of the Government of
MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant.
The detailed terms of the hydro power project agreement are as follows:
1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor.
The
Government of MP will have to acquire land which will submerge on construction of dam and shall
rehabilitate the owners of land.
2. MCC shall have right to operate the hydro power project from date of commencement of
commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government
thereafter. Further,
SPV shall be tax exempt for a period of five years from DCCO i.e. FY17 - FY21.
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The
estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project
is estimated to be commercially operational by April 1, 2016 with two units operational om same day
and one unit each will be operational on April 1, 2017 and April 1, 2018.
4. Means of finance:
Means of Finance INR Million
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100
5. Amount if expenditure estimated in various years is as follows:
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the
principal. The expected principal along with capitalized interest is expected to be INR2, 400 Million
(i.e.INR2100 Million debtplus INR300 Million capitalized interest). The repayment of the same shall
be in 12 equated annual installments starting from FY17.
Brief projections for the period of FY17 to FY21 are given below:
Developments as on March 31, 2015
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From
today we are just left with one more year to complete the project in time. However, the flash floods
which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point
out the loss of lives in the region as you all are well aware of those. Our project has also been badly
hit due to the same and we have been assessing the damage over the last one week. After analyzing
damage, we have made changes in project schedule. Now we will be making only one unit of 150
MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s).
Development as on September 30, 2015
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to
construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in
various courts.
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region
and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its
press release has indicated that they will apply to the higher court on the matter.
As a credit rating analyst on September 30, 2015, on receipt of the high court order, what rating
action you will take:
Question - (Single Choise)
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro
power project on river Shivna in Madhya Pradesh (MP). The project is also of relevance from the
irrigation perspective due to its location and as per the agreement MCC will have to undertake
construction of web of canals, approach road to dam, power house and other ancillary units. MCC is
promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed
government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges
and railway platforms on contract basis for the Government. MCC will have a separate special
purpose vehicle (SPV) floated for this venture. The hydro power project comes under the public
private partnership scheme of the Government of MP, where in the private partner builds owns
operates and transfers (BOOT) the hydro power plant. The detailed terms of the hydro power project
agreement are as follows:
1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor.
The
Government of MP will have to acquire land which will submerge on construction of dam and shall
rehabilitate the owners of land.
2. MCC shall have right to operate the hydro power project from date of commencement of
commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government
thereafter. Further,
SPV shall be tax exempt for a period of five years from DCCO i.e. FY17 - FY21.
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The
estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project
is estimated to be commercially operational by April 1, 2016 with two units operational om same day
and one unit each will be operational on April 1, 2017 and April 1, 2018.
4. Means of finance:
Means of Finance INR Million
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100
5. Amount if expenditure estimated in various years is as follows:
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the
principal. The expected principal along with capitalized interest is expected to be INR2, 400 Million
(i.e.INR2100 Million debt plus INR300 Million capitalized interest). The repayment of the same shall
be in 12 equated annual installments starting from FY17.
Brief projections for the period of FY17 to FY21 are given below:
Developments as on March 31, 2015
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From
today we are just left with one more year to complete the project in time. However, the flash floods
which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point
out the loss of lives in the region as you all are well aware of those. Our project has also been badly
hit due to the same and we havebeen assessing the damage over the last one week. After analyzing
damage, we have made changes in project schedule. Now we will be making only one unit of 150
MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s).
Development as on September 30, 2015
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to
construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in
various courts.
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region
and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its
press release has indicated that they will apply to the higher court on the matter.
On receiving the credit proposal, the banker informed the company that in FY17 the DSCR is below
unity, which is not acceptable to bank. Which of the following is correct?
UNLOCK FULL FEATURED
CCRA-L2 EXAM QUESTIONS
Certified Credit Research Analyst - Level 2
All Official Question Types
Interactive Web-Based Practice Test Software
No Installation or 3rd Party Software Required
Try Self inhance Softwere (Try Demo)
24/7 Customer Support
In just $59.00/$29.5
Practice Test Questions & Answers Demo
Features Of Theexamdumps:
After Purchase Instant Launch
You Can Easily Practice Your Questions
100% Money Back Guarantee
Get 90 Days Free Updates
24/7 Customer Support
Try Free Demos Any Certification Exams
Verified & Updated Questions & Answers
Security & Privacy
The AIWMI CCRA-L2 practice questions from TheExamDumps are designed with care by experts to provide technical accuracy. The practice tests are designed to perfectly match the actual exam atmosphere, providing you with a trustworthy and efficient preparation process.
24/7 Technical Support
We are committed to providing valid exam questions and ensuring trust through verified sources and third-party approvals. Only officially reviewed and AIWMI CCRA-L2 tested preparation materials deliver the most reliable results in the market.
Money Back Guarantee
TheExamDumps AIWMI CCRA-L2 testing engine is user-friendly and designed to help you pass the exam on your first attempt. Focus on understanding the key concepts behind the relevant questions—there's no need to go through every dump.
Instant Download Demo
For your ease, we provide a free demo for the AIWMI CCRA-L2 exam. You can check the accuracy of our practice questions, explore the interface, and review all features before deciding to make a purchase.
What Clients Say About Us
Steven
I just love exam Study Guide for CCRA-L2 certification exam. It is simple, trouble-free and comprehensible without any help. During your exam preparation, you’ll feel as the material has been written especially for you. I qualified CCRA-L2 exam with dazzling scores. I recommend it to you with full confidence!
Kristen Pfeiffer
Passing this certification exam was a dream for me and I have finally achieved that. I am extremely thankful to TheExamDumps for providing such great ways to pass the exam.
William Watson
I passed my AIWMI CCRA-L2 exam and got certified. I just got 93% and I can’t believe it. The experts at TheExamDumps have been doing a great job.
John Beasley
I am extremely happy right now with the CCRA-L2 exam results. I just passed my AIWMI CCRA-L2 exam using your mock tests and I am very thankful to you guys.
The Numbers Say it AllWhy Choose Us
1500
Valid Exams
70,000
SATISFIED CUSTOMERS
95%
Success rate
100%
Strong Customer Relations
Hot Exams
Here are some popular exams you may want to explore — we provide complete practice materials for each of these certification exams.